Reid & Deleye Contractors

Tel: (519) 688-2600

21228 Simcoe Waste Water Treatment Facility

Previous slide
Next slide

Client/Owner

The Corporation of Norfolk County

Architect

R.V. Anderson Associates

Location

Simcoe, ON

Method

Invited Tender

Delivery Date

July 2013

Project Manager

Bill Owen

Site Manager

Ted Comer

Description

Construct WWTF on a brownfield site.

 

Process upgrades: concrete repairs to clarifiers; upgrade 2 primary pump houses; upgrade to 1 sludge pump house; by-pass pumping to suit construction staging; various removals; various plant upgrades including yard piping, drainage, sidewalks, electrical services for new equipment, instrumentation and control equipment.

 

Electrical upgrades: supply and install standby power and replace 6 MCC’s.